DIVISION - I P&C WING OF IDCO, BHUBANESWAR
|
| Development of Special Tourism Area at Puri
|
|
Development of Tourism &
Culture, Govt. of Orissa has
decided to develop STA at Puri
under scheme will Assistance for
large revenue generating
projects, with financial
assistance from Ministry of
Tourism, Govt. of India and
Tourism Department, Govt. of
Orissa. About ac.934.46 land has
been acquired / alienated and
further acquiring of Ac.649.64
of land is under process.
Infrastructure works like
construction of approach road,
bridges and water supply and
power supply is under progress
at an estimated cost of
Rs.1157.80 lakhs. |
|
| Implementation of Urban Haat at Konark.
|
|
The Urban Haat scheme is operated under the Ministry of Textiles, Govt. of India. IDCO has taken up construction of Urban Haat at Konark with an estimated cost of Rs.267.00 lakhs. The work will be completed by January-2007.
|
|
| Implementation of Urban Haat at Puri.
|
|
This work has been also taken up at an estimated cost of Rs.240.00 lakhs. The work has just commenced and will be made functional by December-2007.
|
|
| Development of Chandrabhaga Beach at Konark.
|
|
This work has been awarded to IDCO by Tourism Department, Govt. of Orissa at an estimated cost of Rs.200.00 lakhs. IDCO has taken steps to engage reputed Architect for the work.
|
|
| Construction of Shreekhetra Sanskruti Sangrahalaya.
|
|
It is decided by Tourism & Culture Department to construct Shreekhetra Sanskruti sangrahalaya at Puri and the work has been assigned to IDCO. The total project cost is Rs.300.00 lakhs. IDCO has taken necessary steps to engage reputed Architect for the said work.
|
|
| Construction of Food Court at Puri.
|
|
Tourism & Culture Department has assigned IDCO to construct Food Court near Youth Hostel at Puri at an estimated cost of Rs.100.00 lakhs. Necessary steps has been taken to engage reputed Architect for the work.
|
|
| Construction of Harekrushna Mahatab State Library at Bhubaneswqar.
|
|
Tourism & Culture (Culture) Department, Govt. of Orissa has entrusted IDCO construction of six storied Harekrushna Mahatab State Library at Bhubaneswar. IDCO has taken steps to engage reputed Architect for the work.
|
|
| Construction of G.A.deptt. qtrs. near Sainik School.
|
|
G.A.department, Govt. of Orissa has entrusted IDCO construction work of G.A.qtrs near Sainik School with an estimated cost of Rs.2838.00 lakhs. Construction of 442 qtrs completed and balance work of 200 qtrs. are in progress.
|
|
| Additional works of Odissi Research Centre.
|
|
Tourism & Culture (Culture) Department, Govt. of Orissa has entrusted IDCO construction of Boys & Girls Hostel, staff qtrs. at Odissi Research Centre with an estimated cost of Rs.100.00 lakhs. Steps have been taken by IDCO to select suitable architect for the work.
|
|
| JNV at Konark & Gajapati.
|
|
Navodaya Vidyalaya Samiti, New Delhi has assigned IDCO the works construction of JNV at Konark & Gajapati at an estimated cost of Rs.1200.00 lakhs. The works are under progress and will be completed by March-2007.
|
|
| Development works of Shree Jagannath Temple at Puri.
|
|
A number of works has been assign to IDCO by the Temple Administration, Shree Jagannath Temple, Puri. These are (a) Construction of Yatri Niwas near Shri Gundicha Temple (b) Construction of 4 nos watch Tour near 4 gates of Shree Jagannath Temple. (c) Construction of 30 nos new light post. (d) Renovation & beautification Narendra Tank etc. IDCO has taken necessary steps to engaged reputed Architects for the works.
|
|
| Construction of Lalit Kalamandal.
|
|
Department of Tourism & Culture (Culture), Govt. of Orissa has decided to setup Kalamandal Project near Sainik School with Lalit Kalamandal, Heritage gate, Artesan village etc. and the work has been awarded to IDCO at an estimated cost of Rs.255.32 lakhs. Construction work is in progress.
|
|
| Construction of Tourist Reception Center at Kendrapara.
|
|
Department of Tourism & Culture (Tourism), Govt. of Orissa has entrusted IDCO construction of Tourist Reception Center at Kendrapara at an estimated cost of Rs.0.74 crore. Finishing works are in progress. An amount of Rs. 0.37 Crore has been spent for project till date.
|
|
| IID centre at Khurda.
|
|
The setting up of the IID centers under the Centrally sponsored scheme is to facilitate the Industries in the rural / back ward areas under small and tiny sector units and promote stronger linkages between Agriculture and Industries. The project cost is Rs.718.40 lakhs and it is developed adjacent to NH-5 at Khurda over an area of Ac.150.00. Construction of 4-laning approach road, masonry drain, internal road, power supply and water supply have already been made. An amount of Rs.591.76 lakhs has already been spent for development of the same.
|
|
| IID centre at Rayagada.
|
|
The setting up of the IID centers under the Centrally sponsored scheme is to facilitate the Industries in the rural / back ward areas under small and tiny sector units and promote stronger linkages between Agriculture and Industries. The total project cost is Rs.583.00 lakhs and it is developed at 3 km away from Rayagada town and Pravatipur road over Ac.102.84 of land. Construction of main approach road, internal road, masonry drain, power supply and water supply to door step have already complete with an expenditure of Rs.130.21 lakhs. Now in phase-II development of land at Amlabhata and Kuntalapeta are under procession near Rayagada (JK pur chhak).
|
|
| IID centre at Somanathpur..
|
|
The setting up of the IID centers under the Centrally sponsored scheme is to facilitate the Industries in the rural / back ward areas under small and tiny sector units and promote stronger linkages between Agriculture and Industries. The total project cost is Rs.614.78 lakhs and developed near Somanathpur Industrial Estate over an area of Ac.178.245. Development of main road, internal road, and concrete drain etc. have been started. Power supply and water supply works will be taken up shortly.
|
|
| Food processing Park at Khurda.
|
|
The setting up of the Food park under the centrally sponsored scheme in the state through area approach by way of better utilization of local Agricultural, Forest, & Marine produce and there by improving the rural economy. It is developed adjacent to NH-5 at Khurda with an estimated cost of Rs.990.73 lakhs over Ac.194.65 of land. Construction of main approach road, internal road, masonry drain, power supply and water supply works complete with an expenditure of Rs.466.88lakhs. Construction of administrative-Cum-Laboratory building in finishing stage and other works are in progress.
|
|
| Growth Centre at Jharsuguda.
|
|
The objective of setting up of Growth Centers under centrally sponsored scheme is to facilitate the Industries in rural/back ward areas under small and medium sectors. The project cost is Rs.3989.46 lakhs and in Phase-I. Ac.367.84 land has already been developed and in Phase-II, Ac.206.25 of land under development with main road, internal road, concrete drain, power supply, water supply etc. The road and drain works for the same are under progress. An amount of Rs.1042.73 lakhs has already been spent.
|
|
| Growth Centre at Kalinga Nagar.
|
|
The objective of setting up of Growth Centers under centrally sponsored scheme is to facilitate the Industries in rural/back ward areas under small and medium sectors. The project cost is Rs.4126.73 lakhs and in Phase-I. Ac.100.00 land is under development. In Phase-II, Ac.300.00 of land has been selected and under subjudice which will be finalized shortly. One water supply system has been purchased from MESCO and water supply to JSL and MISL are in force. Construction of main road, branch road, and concrete drain will be taken up shortly for which LOA has already been issued. Power supply and water supply will be made available to each plot. An amount of Rs.2839.22 lakhs has already been spent for this project.
|
|
| Growth Centre at Kesinga.
|
|
The objective of setting up of Growth Centers under centrally sponsored scheme is to facilitate the Industries in rural/back ward areas under small and medium sectors. The project cost is Rs.3306.75 lakhs and in Phase-I. Ac.116.72 of land has been selected at Kesinga and under subjudice. In site-II at Kesinga for Ac.10.00 land has been selected. In site-III at Bolangir over Ac.676.81 has been selected and development of main road, internal road have been completed. An amount of Rs.190.79 lakhs has already been spent for this project.
|
|
| Growth centre at Chhatrapur.
|
|
The objective of setting up of Growth Centers under centrally sponsored scheme is to facilitate the Industries in rural/back ward areas under small and medium sectors. The project cost is Rs.4231.40 lakhs and Ac.125.192 of land has been selected near the TATA Rehabilitation Colony at Sitaipali and Tangarapali. Preparation of layout plan and estimate are under progress.
|
|
| Biotech Park at Bhubaneswar.
|
|
To establish Bio-IT park in the state, it has been decided to develop at Andharua and Dears firm on Public Private Partnership (PPT) model. In first phase it will be setup at Andharua over a land of Ac.63.299 for which construction of compound wall has been completed. An amount of Rs.200.00 lakhs has been received from Science & Technology department, out of which Rs.49.18 lakhs has already been spent.
|
|
| JCDL works at Kalinganagar.
|
|
In Kalinganagar following works are under progress on deposit basis through JCDL
|
a
|
Augmentation of water supply system.
|
Rs.1195.16 lakhs
|
Laying of 600mm dia DI pipe for 7500 mtr completed out of 8300 mtr. Expenditure made Rs.611.18 lakhs. Other works are in progress
|
|
b
|
Development of common facility centre
|
Rs. 25.00 lakhs
|
LOA issued for construction of compound wall and estimate for other work are in progress.
|
|
c
|
Construction of central Tool Room & Training centre.
|
Rs. 300.00 lakhs
|
Selection of Architect is in progress for preparation of plan and estimate..
|
|
d
|
Construction of 2-lane new approach road of 3.05m. length to M/s KJ Ispat, M/s VISA steel & M/s JINDAL
|
Rs. 291.30 lakhs
|
Tendering in process.
|
|
e
|
Augmentation of power distribution facility
|
Rs. 450.00 lakhs
|
Estimate is under process
|
|
|
| Kalinganagar Industrial Complex.
|
|
The objective of setting up of the Industrial complex at Kalinganagar to facilitate the Mega Industries. A good number of Mega Industries are coming up to establish their Industries at Kalinganagar. IDCO has provide common Infrastructure facilities, Rehabilitation to the displaced families at Trijanga and Gobarghati etc. An amount of Rs.1846.96 lakhs has been sanctioned for many developments works out of which some work have been completed and others are in progress.
|
|
| DIVISION - II
|
|
|
|
| CONSTRUCTION OF IDCO, BHUBANESWAR
|
|
Activities: Construction & development
Infrastructure, Roads, Buildings of various
Organisations/Departments of State, Central Govt. & Autonomous
Bodies
|
Sl. No |
Name of the works |
Project
Cost |
Total
Funds
received |
Budget
Provision
06-07 |
Expr.
up to
31.01.07 |
Agency |
Date of
Commencement /Completion |
Physical Progress |
|
|
DEPOSIT WORKS |
(Rs. in lakhs) |
(Rs. in lakhs) |
(Rs. in lakhs) |
(Rs. in lakhs) |
|
|
|
|
01 |
Swimming Pool of Kalinga Stadium |
272.00 |
219.55 |
225.32 |
|
Departmental |
March'05
/March'06 |
Change Room & Swimming Pool: Completed
& Inaugurated. |
|
|
Diving/Warm Up Pool for Swimming
Pool of Kalinga Stadium
(OWN Funds) |
136.96 |
OWN |
50.06 |
30.75 |
Sri B.S.Bhuyan, 334,IRC Village,
Nayapalli Bhubaneswar |
26.10.2006
25.02.2007 |
Warmup Pool: Structurally Pool completed
with waterproofing work.
Diving Pool: Base concrete completed
& waterproofing work is in progress. |
|
02 |
Library Building of SCSTRTI at CRP
Square, Bhubaneswar |
23.00 |
23.00 |
23.00 |
2.93 |
- |
|
Tender finalized, Work order will be
issued and work to be commenced just after completion of
Panchayat Election Process. |
|
03 |
Navodaya Vidyalaya, at Konark (Bill of
IDCO is reimbursed after execution)
|
757.7 Revised |
On Reimbur sement |
411.61 |
387.58 |
Sri Mayadhar Parida At/P.O:Palasuni,
Bhubaneswar |
30.11.2005 / 23.03.07 |
School.Bldg.-Painting ,El & SI work in
progress.
Girl's dormitory: Joinery,E.I. & SI work in progress.
Boy's Dormitory.: GF Plastering work in progress.
Type I,II Qts: Plastering work in
progress Type III Qtrs; Plastering in progress.
Dinning & Kitchen: Finishing work in progress. |
|
04 |
Urban Haat
at Konark |
266.98 Revised |
101.19 |
243.55 |
178.08 |
Sri T. P. Rath Duttatota,
Behind BSNL Office,Puri |
01.07.05
/30.04.06 |
C/wall completed.
Block: A & B- All works completed
except painting.
Open Air Theatre : except painting all works completed.
Toilet: Flooring in progress
Podium: all works completed except
painting. Landscaping, Pathway, water body. Ornamental
work are in progress. |
|
05 |
Urban Haat at Puri
|
240.00 |
90.50 |
40.88 |
16.29 |
M/s.Soor Builders, Chandi Chhak
Cuttack(C/wall work) |
02.06.2006
01.10.2006 |
Sulabh Souchalaya: Completed except
painting by Sulabh International
Compound wall in three sides in Zilla School Backside
and two sides infront
of Womens College completed.
Ornamental work is in progress
Different Units of Urban Haat: Tender is under
finalization. |
|
06 |
GRIDCO (Building finishing works)
|
66.00 |
50.00 |
45.40 |
47.73 |
M/s.Das Builders,Gadasa
hi,Nayapalli,BBSR |
30.05.05
/29.11.05 |
Kota stone fixing and NCI work in
progress. |
|
07 |
Training & Display Centre of State Coir
Development & Training Centre at Teisipur, Puri
|
12.00 |
12.00 |
12.00 |
2.21 |
Departmental |
30.12.06 |
Training Centre: Completed up to lintel
level
Display centre: Foundation work in progress |
|
08 |
60Mtr corridor Road from Giral square to
Sea beach (STA Project) |
|
|
|
|
M/s.Nirmani Engineers & Constructions
Nayapalli, Bhubaneswar |
9months From the date of handing over
of site |
Works up to 800Mtr started. Formation &
moorum sub-base with ICD works completed. |
|
09 |
Two nos Box type Minor Bridge on the
Approach of STA, Puri |
161.82 |
|
|
|
-do- |
6month From the date of handing over
of site |
LOI issued for the work. |
|
10 |
SPECIAL TOURISM AREA sipasarubali, Puri
|
|
|
|
|
|
|
Land Acquisitioned and Possession
taken over
Ac. (Pvt. Land) 364.85
Ac. (-do-) 410.50
Ac.(Govt.land) 159.61
Ac. Approach road 22.52 |
|
|
|
| CONSTRUCTION OF ANGUL DIVISION
|
|
|
|
| ORISSA TABLE TENNIS ASSOCIATION WORKS
|
|
Construction of Indoor Hall, Type-II at Angul:- This work is entrusted to IDCO by the Orissa Table tennis Association, Angul on deposit basis. The estimate is prepared as per the guide lines of the sports Authority at India and administratively approved by the Collector and Chairman at Table Tennis Academy(TTA), Angul for an amount of Rs, 1,12,63,600.00. So far TTA, Angul has deposited an amount of Rs,25.00 lakhs with IDCO, and till Nov.2006. work / expenditure to the tune of Rs,44,63 lakhs has been made.
|
|
| I.G.I.T, SARANG WORKS
|
|
(A) Construction of class Room:- IDCO has been constructed with the construction of 4 nos of gallery type Class Room at an approved estimated cost of Rs, 116.42 lakhs. The Ist floor slabs (roof slabs) of the class rooms have been constructed. The dome portion is completed up to Ist floor level and other finishing works are in progress. Till Jan-2006 an amount of Rs, 43.60 lakhs have been spent (including Super vision Charges) (B) 180 Seated Girl's Hostel Building:- 147, 145, 139 This work includes construction of 2 nos of additional floors (F.F and S.F) over the existing Ground Floor building and construction of Dining / Kitchen block (G.F and S.F) at an approved estimated cost of Rs,160.24 lakhs. The Government of Orissa had approved the tender vide Letter No-2185/dt.8.02.2006 and fund from IGIT, Sarang amounting to Rs,145.00 lakhs has been received. The work has been completed in Dt.31.01.07 before the schedule date of completion i.e 16.02.07 and handed over to the College on Dt.8.02.07.
|
|
| Construction of Type-II ware House at DHH, Angul
|
|
This is a part of the main project constructed all over Orissa under Sector Reform Cell, Bhubaneswar with European Commission grant. These Ware Houses are meant for storing medicine at the District Head Quarter hospital and for this particular work an amount of Rs, 29.48 lakhs is administratively approved. The work has been completed and handed over since 07.03.2006.
|
|
| CONSTRUCTION OF JHARSUGUDA DIVISION
|
|
|
|
| Construction Jharsuguda Division
|
|
1. Activities of Jharsuguda Division:
-
Construction activities of Govt. Departments in Jharsuguda, Sambalpur &
Deogarh Dist.
-
Maintenance of existing Industrial Estates at Sambalpur & Jharsuguda.
-
Acquisition / Alienation of land by IDCO allotment of the same for establishment of industries in Jharsuguda & Sambalpur Districts.
2. Important works / projects, achievements of Jharsuguda Division:
List of works executed during last two years & ongoing works
|
Sl. No.
|
Name of the Project
|
Name of the work
|
Contract value of work (Rs. In lakhs)
|
Total expenditure
(Rs. In lakhs)
|
Remarks
|
|
1
|
BMS Phase-II
|
Up graded CHC at Jujumura
|
10.73
|
9.14
|
Completed & handed over
|
|
2
|
BMS Phase-III
|
Sub-Center at Para
|
3.38
|
3.09
|
Completed & handed over
|
|
3
|
OHSDP (22 Woks)
|
Extension to hospital building & staff qrs.
to CHC-II at
Charmal
|
39.45
|
38.83
|
Completed & handed over
|
|
4
|
RCH
|
LR & OT Complex at Loida
|
8.15
|
8.91
|
Completed & handed over
|
|
5
|
-do-
|
LR & OT Complex at Jujumura
|
8.48
|
8.31
|
Completed & handed over
|
|
6
|
OH & FW
|
Regional Diagnostic Center at Burla
|
47.65
|
46.93
|
Completed & handed over
|
|
7
|
AH & VS
|
Frozen Semen Bank Laboratory at Chiplima
|
26.49
|
24.21
|
Completed & handed over
|
|
8
|
Jail Building
|
Construction of 3 Nos. E Type Qrs. & 5 Nos. F Type Qrs. at Sub-Jail, Jharsuguda
|
21.51
|
22.99
|
Completed & handed over
|
|
9
|
Sambalpur University
|
Provision for Acoustics Arrangement, Internal Electrification, Sound System & seating arrangement in the
auditorium of Sambalpur
University of Burla.
|
29.18
|
29.12
|
Completed & handed over
|
|
10
|
Sector Reform Cell
|
Construction of
(Type-II) Ware House at DHH, Sambalpur
|
25.36
|
22.61
|
Completed & handed over
|
|
11
|
-do-
|
Construction of (Type-I) Ware House at DHH, Jharsuguda
|
22.10
|
21.82
|
Completed & handed over
|
|
12
|
OHSDP (PKG-5)
|
New Construction, One Time Repair & Renovation of DHH, Sambalpur
|
175.40
|
174.93
|
Completed & handed over
|
|
13
|
-do-
|
New Construction, One Time Repair & Renovation of DHH, Jharsuguda
|
107.93
|
126.10
|
Completed & handed over
|
|
14
|
-do-
|
New Construction, One Time Repair & Renovation of DHH, Deogarh
|
114.07
|
127.08
|
Completed & handed over
|
|
15
|
-do-
|
New Construction, One Time Repair & Renovation of CHC-II at Chhatabar
|
38.48
|
36.43
|
Completed & handed over
|
|
16
|
-do-
|
New Construction, One Time Repair & Renovation of CHC-II at Garposh
|
39.24
|
39.53
|
Completed & handed over
|
|
17
|
-do-
|
New Construction, One time Repair & Renovation of SDH, Kuchinda
|
82.66
|
69.83
|
Completed & handed over
|
|
18
|
-do-
|
New Construction, One Time Repair & Renovation of CHC-II at Kuntra
|
46.00
|
45.14
|
Completed & handed over
|
|
19
|
-do-
|
New Construction, One Time Repair & Renovation of CHC-II at Mundrajore
|
39.59
|
43.00
|
Completed & handed over
|
|
20
|
-do-
|
New Construction, One Time Repair & Renovation of CHC-I at Rairakhol
|
53.34
|
61.17
|
Completed & handed over
|
|
21
|
PMGSY
|
Improvement of Road & CD works under PMGSY in the
Dist. Of Jharsuguda for Package No. OR-14-12/V.
|
323.48
|
227.68
|
Work under progress likely to be completed by 31.03.2007
|
|
22
|
Industrial Growth Center
|
Construction of 1.54 Km long main road for growth center at Jharsuguda including 5 Nos. RCC slab culvert of 1.60mx1.0m
(WMM, BM & SDBCJ
|
92.00
|
92.00
|
Completed
|
|
23
|
-do-
|
Const. Of Main Road with C.D works at Growth Center,
Jharsuguda
|
91.33
|
25.18
|
Work under progress likely to be completed by 31-03-2007
|
|
24
|
-do-
|
Const. Of Branch Road with C.D works (East side of main
road) at Growth Center, Jharsuguda
|
87.45
|
15.94
|
Work under progress likely to be completed by 31.03.2007
|
|
25
|
-do-
|
Const. Of Branch Road with C.D works (West side of main road) at Growth Center, Jharsuguda.
|
89.33
|
15.09
|
Work under progress likely to be completed by 31.03.2007
|
|
26
|
-do-
|
Const. Of RCC Drain, Retaining Wall & C.D works at Growth Center, Jharsuguda.
|
80.80
|
9.44
|
Work under progress likely to be completed by 31.03.2007
|
3. Rules / Regulations / Forms relevant for services being provided by
IDCO:
May be provided from head office.
4. Any other information relevant for public knowledge:
Presently developed land having good infrastructure facility is available at Jharsuguda which is suitable for establishment of Micro, Small & Medium Industries. Interested persons / companies may contact CGM (ID), IDCO, Bhubaneswar for the purpose.
|
|